Case Studies
Hubert has conducted out many projects over the years. You will find our projects in new construction (EPC) projects as well as renovation and optimization of existing factories.
Below are some examples that will be gradually supplemented. Are you looking for a project example (similar to your situation) and you cannot find what you are looking for then contact us. We may then be able to compile a compilation of a similar project that we have already carried out for you.
![Hubert microscreen Hubert microscreen](https://hubert.nl/wp-content/uploads/2020/08/20160421_171531-scaled-e1597396581717.jpg)
Anglian Water / Elsham Water Treatment Centre
Potable Water Production Plant
United Kingdom
Project introduction
For the Elsham water treatment plant owned by Anglian Water, Hubert was awarded the contract for delivery and installation of 3 micro strainers. The facility in Elsham processes 75 million litres (16.5 million gallons) of water every day. The plant supplies much of the drinking water for Northern Lincolnshire. Anglian Water had a lot of problems with zebra mussels that clog the water inlet pipe from the river Ancholme. The zebra mussel, Dreissena Polymorpha, is a specied of small freshwater Shellfish.
Anglian Water / Elsham Water Treatment Centre
Potable Water Production Plant
United Kingdom
Project introduction
For the Elsham water treatment plant owned by Anglian Water, Hubert was awarded the contract for delivery and installation of 3 micro strainers. The facility in Elsham processes 75 million litres (16.5 million gallons) of water every day. The plant supplies much of the drinking water for Northern Lincolnshire. Anglian Water had a lot of problems with zebra mussels that clog the water inlet pipe from the river Ancholme. The zebra mussel, Dreissena Polymorpha, is a specied of small freshwater Shellfish.
![Hubert case study JGC Gulf Bapco Hubert case study JGC Gulf Bapco](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-JGC-Gulf-Bapco-2-e1597737862831.jpg)
BAPCO / JGC Gulf International
HLPH Facility – Refinery / Seawater intake filtration system
Bahrain
Project introduction
Hubert was awarded the contract from JGC Gulf International Co. Ltd. for the Bahrain Petroleum Company (BAPCO) to improve the seawater filtration system at their HLPH facility. The Sea Water Intake Filtration system had to be delivered including all complementary equipment, items and services to meet the design and environmental conditions. Hubert was responsible for ensuring that the specification was met for all deliveries and services in subcontracting.
BAPCO / JGC Gulf International
HLPH Facility / Seawater intake filtration system
Bahrain
![Hubert case study JGC Gulf Bapco Hubert case study JGC Gulf Bapco](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-JGC-Gulf-Bapco-2-e1597737862831.jpg)
![Hubert case study JGC Gulf Bapco Hubert case study JGC Gulf Bapco](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-JGC-Gulf-Bapco-2-e1597737862831.jpg)
![Hubert case study JGC Gulf Bapco Hubert case study JGC Gulf Bapco](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-JGC-Gulf-Bapco-2-e1597737862831.jpg)
Project introduction
Hubert was awarded the contract from JGC Gulf International Co. Ltd. for the Bahrain Petroleum Company (BAPCO) to improve the seawater filtration system at their HLPH facility. The Sea Water Intake Filtration system had to be delivered including all complementary equipment, items and services to meet the design and environmental conditions. Hubert was responsible for ensuring that the specification was met for all deliveries and services in subcontracting.
![Hubert case strudy wetterskip Fryslan Hubert case strudy wetterskip Fryslan](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-strudy-wetterskip-Fryslan-scaled-e1597746584538.jpg)
![Hubert case strudy wetterskip Fryslan Hubert case strudy wetterskip Fryslan](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-strudy-wetterskip-Fryslan-scaled-e1597746584538.jpg)
![Hubert case strudy wetterskip Fryslan Hubert case strudy wetterskip Fryslan](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-strudy-wetterskip-Fryslan-scaled-e1597746584538.jpg)
Wetterskip Fryslan
Wastewater Treatment Plant (WWTP)
Netherlands
Project introduction
For the Birdaard waste water treatment plant owned by Wetterskip Fryslân – the regional water board – Hubert was awarded the contract for delivery and installation of a new clarifier. This waste water treatment plant, located in the north of the Netherlands, is already operating with the aid of Hubert thickeners, aerators and clarifiers.
Wetterskip Fryslan
Wastewater Treatment Plant (WWTP)
Netherlands
![Hubert case strudy wetterskip Fryslan Hubert case strudy wetterskip Fryslan](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-strudy-wetterskip-Fryslan-scaled-e1597746584538.jpg)
![Hubert case strudy wetterskip Fryslan Hubert case strudy wetterskip Fryslan](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-strudy-wetterskip-Fryslan-scaled-e1597746584538.jpg)
![Hubert case strudy wetterskip Fryslan Hubert case strudy wetterskip Fryslan](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-strudy-wetterskip-Fryslan-scaled-e1597746584538.jpg)
Project introduction
For the Birdaard waste water treatment plant owned by Wetterskip Fryslân – the regional water board – Hubert was awarded the contract for delivery and installation of a new clarifier. This waste water treatment plant, located in the north of the Netherlands, is already operating with the aid of Hubert thickeners, aerators and clarifiers.
![Hubert case study EDF REEL Flamanville Hubert case study EDF REEL Flamanville](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-EDF-REEL-Flamanville-e1597749544401.jpg)
![Hubert case study EDF REEL Flamanville Hubert case study EDF REEL Flamanville](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-EDF-REEL-Flamanville-e1597749544401.jpg)
![Hubert case study EDF REEL Flamanville Hubert case study EDF REEL Flamanville](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-EDF-REEL-Flamanville-e1597749544401.jpg)
EDF / REEL International
Flammanville Nuclear Power Plant 1 & 2
France
Project introduction
Hubert was awarded the contract for EDF’s nuclear power plant Flamanville 1 & 2 in France for replacement of screening drums via the collaboration with partner Reel International, known from their extensive experience in nuclear projects. Screening drums are part of the seawater intake filtration system. Hubert was responsible for ensuring that the specification was met for all deliveries in subcontracting. This project is a technical outstanding performance and consolidates and strengthens Hubert’s position in this market segment.
EDF / REEL International
Flammanville Nuclear Power Plant 1 & 2
France
![Hubert case study EDF REEL Flamanville Hubert case study EDF REEL Flamanville](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-EDF-REEL-Flamanville-e1597749544401.jpg)
![Hubert case study EDF REEL Flamanville Hubert case study EDF REEL Flamanville](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-EDF-REEL-Flamanville-e1597749544401.jpg)
![Hubert case study EDF REEL Flamanville Hubert case study EDF REEL Flamanville](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-EDF-REEL-Flamanville-e1597749544401.jpg)
Project introduction
Hubert was awarded the contract for EDF’s nuclear powerplant Flamanville 1 & 2 in France for replacement of screening drums via the collaboration with partner Reel International, known from their extensive experience in nuclear projects. Screening drums are part of the seawater intake filtration system. Hubert was responsible for ensuring that the specification was met for all deliveries in subcontracting. This project is a technical outstanding performance and consolidates & strengthens Hubert’s position in this market segment.
![Hubert case study Yanbu II Hubert case study Yanbu II](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Yanbu-II-5-scaled-e1597752816381.jpg)
![Hubert case study Yanbu II Hubert case study Yanbu II](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Yanbu-II-5-scaled-e1597752816381.jpg)
![Hubert case study Yanbu II Hubert case study Yanbu II](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Yanbu-II-5-scaled-e1597752816381.jpg)
SWCC / Marafiq / Saudi Archirodon
Yanbu II Power and Desalination Plant
Saudi Arabia
Project introduction
Hubert was awarded the contract for delivery of the marine package or seawater intake filtration system. Hubert was responsible for ensuring that the specification was met for all deliveries in subcontracting.
SWCC / Marafiq / Saudi Archirodon
Yanbu II Power & Desalination Plant
Saudi Arabia
![Hubert case study Yanbu II Hubert case study Yanbu II](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Yanbu-II-5-scaled-e1597752816381.jpg)
![Hubert case study Yanbu II Hubert case study Yanbu II](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Yanbu-II-5-scaled-e1597752816381.jpg)
![Hubert case study Yanbu II Hubert case study Yanbu II](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Yanbu-II-5-scaled-e1597752816381.jpg)
Project introduction
Hubert was awarded the contract for delivery of the marine package or seawater intake filtration system. Hubert was responsible for ensuring that the specification was met for all deliveries in subcontracting.
![Hubert Case Study Hadjret en Nouss Hubert Case Study Hadjret en Nouss](https://hubert.nl/wp-content/uploads/2020/10/IMG-20160219-WA0001-1-e1602503179325.jpg)
![Hubert Case Study Hadjret en Nouss Hubert Case Study Hadjret en Nouss](https://hubert.nl/wp-content/uploads/2020/10/IMG-20160219-WA0001-1-e1602503179325.jpg)
![Hubert Case Study Hadjret en Nouss Hubert Case Study Hadjret en Nouss](https://hubert.nl/wp-content/uploads/2020/10/IMG-20160219-WA0001-1-e1602503179325.jpg)
Hadjret En Nouss
Combined Cycle Power Plant
Algeria
Project introduction
Hubert was awarded the contract in collaboration with Taprogge Germany to supply the seawater screening system for the SKH Powerplant in Algeria.
Hadjret En Nouss
Combined Cycle Powerplant
Algeria
![Hubert Case Study Hadjret en Nouss Hubert Case Study Hadjret en Nouss](https://hubert.nl/wp-content/uploads/2020/10/IMG-20160219-WA0001-1-e1602503179325.jpg)
![Hubert Case Study Hadjret en Nouss Hubert Case Study Hadjret en Nouss](https://hubert.nl/wp-content/uploads/2020/10/IMG-20160219-WA0001-1-e1602503179325.jpg)
![Hubert Case Study Hadjret en Nouss Hubert Case Study Hadjret en Nouss](https://hubert.nl/wp-content/uploads/2020/10/IMG-20160219-WA0001-1-e1602503179325.jpg)
Project introduction
Hubert was awarded the contract in collaboration with Taprogge Germany to supply the seawater screening system for the SKH Powerplant in Algeria.
![Hubert case study Kurskaya power plant Hubert case study Kurskaya power plant](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Kurskaya-power-plant-5-e1597755500413.jpg)
![Hubert case study Kurskaya power plant Hubert case study Kurskaya power plant](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Kurskaya-power-plant-5-e1597755500413.jpg)
![Hubert case study Kurskaya power plant Hubert case study Kurskaya power plant](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Kurskaya-power-plant-5-e1597755500413.jpg)
ASE / Rosatom State Corp. Engineering Division
Kurskaya Nuclear Power plant II
Russian Federation
Project introduction
Hubert was awarded the contract by ASE (Rosatom State Corporation Engineering Division) to supply water-treatment units for the GA make-up water installation at the Kurskaya Nuclear Power Plant.
ASE / Rosatom State Corp. Engineering Division
Kurskaya Nuclear Power plant II
Russian Federation
![Hubert case study Kurskaya power plant Hubert case study Kurskaya power plant](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Kurskaya-power-plant-5-e1597755500413.jpg)
![Hubert case study Kurskaya power plant Hubert case study Kurskaya power plant](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Kurskaya-power-plant-5-e1597755500413.jpg)
![Hubert case study Kurskaya power plant Hubert case study Kurskaya power plant](https://hubert.nl/wp-content/uploads/2020/08/Hubert-case-study-Kurskaya-power-plant-5-e1597755500413.jpg)
Project introduction
Hubert was awarded the contract by ASE (Rosatom State Corporation Engineering Division) to supply water-treatment units for the GA make-up water installation at the Kurskaya Nuclear Power Plant.
![Drum Screen - Shell Pernis refurbishment - Hubert Drum Screen - Shell Pernis refurbishment - Hubert](https://hubert.nl/wp-content/uploads/2021/02/Shell-Pernis-reference-2013-overhaul-drumscreen-1-scaled-e1612961064438.jpg)
![Drum Screen - Shell Pernis refurbishment - Hubert Drum Screen - Shell Pernis refurbishment - Hubert](https://hubert.nl/wp-content/uploads/2021/02/Shell-Pernis-reference-2013-overhaul-drumscreen-1-scaled-e1612961064438.jpg)
![Drum Screen - Shell Pernis refurbishment - Hubert Drum Screen - Shell Pernis refurbishment - Hubert](https://hubert.nl/wp-content/uploads/2021/02/Shell-Pernis-reference-2013-overhaul-drumscreen-1-scaled-e1612961064438.jpg)
Shell Netherlands Refinery BV / Jacobs
Pernis Refinery
Netherlands
Project introduction
Hubert took care or the overhaul a water intake screen for Pernis refinery, the largest refining site in Europe and one of the largest worldwide. It was a complex project from the removal of the complete screen, renovation under controlled conditions, to reassembly on site.
Shell Netherlands Refinery BV / Jacobs
Pernis Refinery
Netherlands
![Drum Screen - Shell Pernis refurbishment - Hubert Drum Screen - Shell Pernis refurbishment - Hubert](https://hubert.nl/wp-content/uploads/2021/02/Shell-Pernis-reference-2013-overhaul-drumscreen-1-scaled-e1612961064438.jpg)
![Drum Screen - Shell Pernis refurbishment - Hubert Drum Screen - Shell Pernis refurbishment - Hubert](https://hubert.nl/wp-content/uploads/2021/02/Shell-Pernis-reference-2013-overhaul-drumscreen-1-scaled-e1612961064438.jpg)
![Drum Screen - Shell Pernis refurbishment - Hubert Drum Screen - Shell Pernis refurbishment - Hubert](https://hubert.nl/wp-content/uploads/2021/02/Shell-Pernis-reference-2013-overhaul-drumscreen-1-scaled-e1612961064438.jpg)
Project introduction
Hubert took care or the overhaul a water intake screen for Pernis refinery, the largest refining site in Europe and one of the largest worldwide. It was a complex project from the removal of the complete screen, renovation under controlled conditions, to reassembly on site.
Customer Stories
Project: Replacement of gutter and clearing bridge settling tank at WWTP Birdaard
The elaboration of the drawings with accompanying calculations in the preparation phase were well worked out. The construction of the new gutter and bridge was installed satisfactorily by employees and especially the foreman. The project was completed on time, both financially and in the delivery of product certificates and revision. A great project and end result was achieved through synergy between client and contractor.
Wetterskip Fryslan, Netherlands, mr. R.T. van der Zee, Design coordinator - Director