Projectintroductie

Hubert kreeg het contract van ASE (Rosatom State Corporation Engineering Division) om waterbehandelingsunits te leveren voor de GA make-up waterinstallatie in de Kurskaya kerncentrale.

Downloaden PDF
Hubert Case Study Kurskaya Power Plant 0 E1597755824280
Hubert Casestudie Koerskaja Energiecentrale 5 E1597755492687
Hubert Case Study Kurskaya Power Plant

Hubert Bevoorrading

Hubert’s supplied Hubert travelling band screens accommodated with a fish return system. The band screens are based on a skid design and are delivered as a package for immediate installation and operation on-site. All rotating parts are fabricated in 316L stainless steel.

The complete band screen housing is produced from carbon steel provided with a high-quality, multilayer epoxy coating for protection against local environmental conditions. The design flow capacity for each band screen is 9,000m3 per hour. The square mesh opening in the screen panels is 2 x 2 mm.

Belangrijke cijfers

  • Location: Russian Federation
  • Hubert products: traveling band screen
  • Materials: stainless steel 316L